...By Theo LeggettBusiness correspondent, BBC NewsA dense forest of cranes, visible for miles around, marks the spot where the UK s first new nuclear plant in a generation is being built, at Hinkley Point in Somerset...
Ministers to speed up delivery of new power lines for clean energy
... This includes pledges to quadruple offshore wind to 55GW, triple solar power to 50GW, double onshore wind to 35GW, and back Hinkley Point and Sizewell C nuclear power stations...
The truth about heat pumps and the power needed to run them
... Hinkley Point C in Somerset is massively over budget and is now expected to start operating in 2026 - A, next to Sizewell B, but it has been stuck in planning for over a decade...
EDF's UK profits soar after electricity price hikes
... It said it planned to invest a further £13bn in the UK in the next three years, largely at Hinkley Point C, the new nuclear power station being built in Somerset that is due to open in 2027...
Hinkley Point C construction worker killed in 'traffic incident'
...A construction worker has died while working at the Hinkley Point C nuclear power station site in Somerset...
Labour: Keir Starmer claims fact-checked
... On nuclear energy, in the 12 years of Conservative (and Conservative-led) government, work has started on one new nuclear plant - at Hinkley Point C, which is due to open in 2027...
Nuclear power: What role can it play in the UK's climate future?
... Nuclear power: What role can it play in the UK s climate future? The UK government says that nuclear is critical to its climate plans, but can it deliver? Jordan Dunbar from The Climate Question podcast has been given rare access to Hinkley Point B and Point C to learn more about what it will take to build eight new reactors by 2050...
Hinkley Point C delayed by a year as cost goes up by £3bn
...The nuclear power station being built at Hinkley Point will start operating a year later than planned and will cost an extra £3bn, EDF has said...
Ministers to speed up delivery of new power lines for clean energy
By Ione Wells & Joshua Nevett BBC Politics
Energy Secretary Grant Shapps has told The Bbc the government plans to " halve" The Time it takes for more Power Lines to be built across the UK.
Mr Shapps will set out proposals to speed up the construction of substations, underground lines and pylons for Clean Energy on Friday.
The National Grid says five times more Power Lines need to be built in The Next seven years than in The Past 30.
But it says planning reforms will be needed to get them built.
Last July, Energy expert Nick Winser as the Electricity Networks Commissioner to advise on how this could be done.
The Bbc has been told Mr Winser has presented his proposals to Downing Street and they were " well received".
Industry experts widely expect Mr Winser's report to include recommendations on streamlining the processing of planning applications for electricity transmission infrastructure, such as pylons and substations.
The plans could provoke a political backlash in some parts of the country, particularly the East Coast of England and Scotland.
A group of Conservative MPs, including environment secretary Therese Coffey , have campaigned against new electricity pylons being routed through their constituencies in Suffolk and Norfolk.
Many areas likely to be impacted are Tory safe seats in East Anglia , where a network of major wind Power projects are trying to bring their clean Power onshore.
Government insiders have said that they were having to work very carefully with MPs from across The House of Commons on their plans.
Mr Shapps told The Bbc 's World at One programme that he would be issuing Mr Winser's recommendations this Friday along with " some government immediate response".
" The idea is to halve the amount of time it takes to get these connections going, " Mr Shapps said.
Mr Shapps's department said the government would welcome Mr Winser's report and set out its response to his proposals at a later Date .
, Mr Winser said he would proposes ways to halve The Delivery time of electricity projects from 14 to seven years.
Political flash pointBoth major Political Parties have set out Energy plans that will require more overground and underground Power Lines to achieve.
Labour has announced plans to Power the UK with "100% clean and affordable Power " by 2030. This includes pledges to quadruple offshore wind to 55GW, triple Solar Power to 50GW, double onshore wind to 35GW, and back Hinkley Point and Sizewell C Nuclear Power stations.
The government has said it would decarbonise Power by 2035, including up to 50GW of offshore wind, 10GW of hydrogen production by 2030, and investment in Nuclear Power .
The National Grid has said more overground and underground cables are needed to transport more wind, nuclear and Solar Power - and to respond to a growing demand for electricity as more people use technology such as electric cars.
It says by 2030, it needs to build five times as many transmission lines as have been built in The Last 30 years, which would involve reforming the planning system and shortening the application process.
It says decisive action from government, industry and Ofgem is critical to achieve this.
Labour insiders have said " we will do whatever is necessary" if The Party wins The Next general election.
Shadow Climate Change and net zero secretary Ed Miliband said: " For thirteen years, the Conservatives have prioritised NIMBY (" Not In My Back Yard" ) backbenchers who oppose clean Power above the interests of the British People .
" Their refusal to tackle delays in the planning system has robbed Britain from heaving cleaner, cheaper Power . "
The Department for Energy Security and Net Zero said it was " committed to achieving Energy security and expanding the capacity of The National grid is crucial to this" but that " delivering this means bringing reform to the planning process and making sure communities feel they are directly benefitting from cheaper, secure, low-carbon Energy ".
Boosting Renewable Energy - and The Massive infrastructure that comes with it - is likely to be a dividing line between parties in some seats at The Next election.
Some renewable infrastructure has caused divisions even among green Campaigners - with some Green Party councillors campaigning against solar farms on their local landscape.