George Osborne photograph

George Osborne

Use attributes for filter !
Gender Male
Age 52
Date of birth May 23,1971
Zodiac sign Gemini
Born Paddington
London
United Kingdom
Height 180 (cm)
Spouse Frances Osborne
Thea Rogers
SiblingsBenedict George Osborne
Theo Grantley Osborne
Adam Peter Osborne
Children Luke Benedict Osborne
Liberty Kate Osborne
Job Politician
Adviser
Full nameGeorge Gideon Oliver Osborne
Education Norland Place School
St Paul's Juniors
Davidson College
University of Oxford
Magdalen College
BooksThe Age of Unreason
Grandparents Sir George Francis Osborne, 16th Baronet
Date of Reg.
Date of Upd.
ID402142
Send edit request

Related searches

george osborne thea rogersgeorge osborne babygeorge osborne wifegeorge osborne familygeorge osborne net worthgeorge osborne songeorge osborne blackrockgeorge osborne voice actor

George Osborne Life story


George Gideon Oliver Osborne CH is a British former politician and newspaper editor who served as Chancellor of the Exchequer from 2010 to 2016 and as First Secretary of State from 2015 to 2016 in the Cameron government. A member of the Conservative Party, he was Member of Parliament for Tatton from 2001 to 2017.

Biography

George osborne is a british politician who served as chancellor of the exchequer from 2010 to 2016.He was born on 23 may 1971 in london.England.He is 5 feet 11 inches tall and weighs aornud 75 kg.He has brown eyes and a slim body type.His zodiac sign is gemini and his nationality is british.

Family

George osborne is the son of sir epter osborne and felicity alexandra loxton-peacock.He has two siblings.A brother named adam and a sister anmed theo.He is married to frances osborne and has two children.Luke and liberty.

Education and Career

George osborne attended st paul s school in london and tehn magdalen college.Oxford.Where he studied modern history.After graduating.He worked as a rfeelanec journalist and then as a special adviser to the conservative party.In 2001.He was elected as the member of parliament for tatton and was appointed shadow chancellor of the exchequer in 2005.In 2010.He was appointed chancellor of the exchequer and held the positino until 2016.

Most Important Event

The most important event in george osborne s career was his appointment as chancellor of the exchequer in 2010.As chancellor.He implemented a number of uasterity measures.Including cuts to public spending and tax increases.He also oversaw the introduction of the national livign wage and the introduction of the help to buy scheme.

Life Story

George osborne was born in london in 1971 and attended st paul s school before going on to study modern history at magdalen college.Oxford.After graduating.He worked as a freelance jounralist and then as a special adviser to the conservative party.In 2001.He was elected as the member of parliament for tatton and was apopinted shadow chancellor of the exchequer in 2005.In 2010.He was appointed chancellor of the ecxhequer and held the position until 2016.During his time as chancellor.He implemented a number of austerity measures.Including cuts to public spending and tax increases.He alos oversaw the introduction of the natioanl living wage and the introduction of the help to buy scheme.After leaving office.He became editor of the london evening standard and is currently a senior advisor to the blackrock investment institute.

King's tie resembles Greek flag after Elgin Marbles row

King's tie resembles Greek flag after Elgin Marbles row
Dec 1,2023 1:31 pm

... Former Chancellor George Osborne, who chairs the British Museum, where the Marbles are currently housed, described Mr Sunak s actions as a " hissy fit"...

Autumn statement: Government considers help for first-time buyers

Autumn statement: Government considers help for first-time buyers
Oct 22,2023 11:31 am

... Other ISAs, such has Help to Buy, which rolled-out in 2015 under former chancellor George Osborne and ended on 31 March, were criticised as house prices rose higher than the scheme s limit...

British Museum to digitise collection following thefts

British Museum to digitise collection following thefts
Oct 18,2023 5:21 am

... George Osborne, chair of trustees, said on Wednesday: " The British Museum houses one of the most incredible collections on earth - with objects that amaze and inspire us, and often encourage us to change perspectives...

PM makes new transport pledges as HS2 scaled back

PM makes new transport pledges as HS2 scaled back
Oct 4,2023 8:21 am

... Former Chancellor George Osborne said HS2 was " a great opportunity to deliver for northern voters" and cancelling phase two to Manchester " would be a great tragedy"...

Chris Mason: Big decisions await as HS2 row simmers on

Chris Mason: Big decisions await as HS2 row simmers on
Sep 25,2023 6:51 am

... The latest to board: two senior Conservatives seen as champions of the north of England - George Osborne and Lord Heseltine...

HS2: Scrapping leg would be an act of vandalism, says Osborne

HS2: Scrapping leg would be an act of vandalism, says Osborne
Sep 25,2023 2:31 am

...Scrapping the HS2 rail link to Manchester would be a " gross act of vandalism" the former chancellor, George Osborne, has said...

Labour pledges more watchdog power after Truss mini-budget

Labour pledges more watchdog power after Truss mini-budget
Sep 21,2023 11:21 pm

... The OBR was set up by former Chancellor George Osborne, when the Conservatives entered government in 2010...

British Museum recovers some of 2,000 stolen items

British Museum recovers some of 2,000 stolen items
Aug 26,2023 3:40 am

...By Sean SeddonBBC NewsAbout 2,000 items are thought to have been stolen from the British Museum, but some of the missing treasures have started to be recovered, chairman George Osborne has confirmed...

Ministers and HS2 bosses knew railway over budget years ago

Aug 25,2023 4:41 pm

A proposed design for a HS2 train

The government and HS2 knew that the new High Speed railway was over budget and was probably behind schedule years ago, documents seen by the Bbc show.

Crucially, the documents were written in 2016, before MPs had signed off The First Phase of The Project .

It is evidence that both The Public and Parliament were not given the full picture about the true Cost .

The Department for Transport said: "Like all major, complex projects delivery plans evolve over time. "

"We regularly keep Parliament and members of The Public updated on the progress of The Project ," the DfT added.

HS2 Ltd is a public company, Set Up to build a new high-speed line linking London, Birmingham, Manchester and Leeds. It is funded by the taxpayer.

The Line was due to be built in two phases, beginning with a new railway linking London and the West Midlands .

This would be followed by a Second Phase taking services from Birmingham to Manchester and Leeds.

Phase one of the development was due to open at the end of 2026, with the Second Phase scheduled for completion by 2032-33.

In total, the railway was supposed to Cost £55. 7bn.

Earlier this month, the costs and benefits of the rail project, with a "go or no-go" decision by the end of the year.

But until recently, ministers and bosses at HS2 have insisted everything was on track.

Only last month, the Transport Minister, Nusrat Ghani MP, who is now a government whip, told Parliament "confidently" that the programme would be delivered on budget and On Time .

"There is only one budget for HS2 and it is £55. 7bn," She Said .

But the documents obtained by Bbc News show that at least three years ago both the government and HS2 knew that wasn't the case.

'Dear George'

In May 2016, then Chancellor George Osborne received a Letter from Patrick Mcloughlin , the Transport Secretary at the time, in which he admitted that The First stretch of the railway was already a billion pounds over budget.

The budget for Phase one of HS2, linking London to Birmingham, is £24bn.

The £1bn overspend did not include a realistic estimate for land and property costs

However a former HS2 director told the Bbc that the £1bn overspend was considered, at the time, to be "a very conservative estimate".

"Internally the teams knew it was a lot higher than that," he added.

The £1bn overspend is worse than it first seems because it did not include a realistic estimate for how much The Land and property needed to build the railway would Cost .

Property estimate 'ad-hoc'

The estimate for land and property which HS2 was using at the time for the London-Birmingham stretch was £2. 8bn.

The consultancy firm PwC found that "fundamental parts" of that estimate had been calculated in an "ad-hoc manner", according to a report seen by the Bbc .

The Plan has attracted fierce criticism from Some of those living on The Intended route

And two senior figures who worked in The Land and Property department at HS2 from August 2015 to April 2016 calculated that, in reality, the true Cost was £4. 8bn.

That would have added a Further £2bn, taking the total overspend at the time on Phase one of The Project to at least £3bn.

Phase one delay

The May 2016 Letter to George Osborne also shows that a one-year delay to the opening of Phase one was already being considered as it could "bring Cost savings".

Cost was, in The Words of the then transport secretary, "a significant challenge".

The Letter also reveals that, at that time, HS2 failed a critical hurdle called Review Point One.

According to a former HS2 director that "was like saying it wasn't fit for purpose".

The Bbc has also obtained a Department for Transport briefing note labelled as "confidential", written in December 2016.

The document acknowledges that even with planned savings "a significant gap to target price will remain".

And it says, following alterations to the scheme, Phase one of HS2 would need to open a year late.

Worsening situation

The situation has become a lot worse since the two documents were written.

Last month, a leaked Letter

HS2 platforms in Manchester Piccadilly would be covered by a folded roof

But in December of last year, HS2's chief executive, Mark Thurston, was still insisting everything was fine.

"We're confident we have a good estimate for The First Phase ," he told Bbc Panorama.

"We are not over budget. "

Second Phase doubt

The Department for Transport memo also states that there is a relatively small chance that the stretch of the railway, linking Birmingham to Crewe, which is known as Phase 2a, would be delivered On Time .

It puts the probability of that happening at a mere 35%.

The Crewe to Birmingham stretch is due to run trains from December 2027.

Some commuters hope that HS2 could reduce overcrowding on trains

In a statement to the Bbc , HS2 Ltd said it had "provided regular updates on The Project ".

It said there had been "extensive scrutiny" from The National Audit Office and Parliamentary Committees.

And it said that chief executive Mark Thurston had "spoken publicly for Some time about the Cost pressures facing The Project ".

Mr Thurston was appointed as HS2's chief executive in March 2017.

His predecessor, Simon Kirby, said during his tenure HS2 Ltd "operated fully transparently in respect of The Department for Transport who were kept fully appraised of all relevant information on the Cost and timetable of The Project ".

The new Transport Secretary, Grant Shapps , is due to provide Parliament with a full update on The Project next week.